not-allowed-link

Water Street Bridge

Winner icon
Infrastucture Projects Winner

About the project

Project category

Infrastructure

Company / Project parties

Kilnbridge

Location

United Kingdom

Images

Water Street Bridge

The construction of the new Water Street Bridge provides both a road and pedestrian link between Montgomery Square within the existing Canary Wharf estate and the new Wood Wharf Development. The bridge itself consists of a single leaf bascule bridge, weighing 185t and spanning 26.7m over the Bellmouth Passage, part of the former West India Dock, between the pivot point within the East Abutment bascule chamber and the nose bearing on the West Abutment.

The West Abutment consists of a number of vertical structures supported on bearing piles through the existing promenade, notably two feature concrete columns supporting the bridge elastometric bearings. The approach deck spans over existing LUL property, with a lift out element to allow for emergency access to the structure below.

The East Abutment is a semi-submerged concrete structure founded on 1200mm diameter bored marine piles, with permanent steel casings sealed into the Lambeth Beds below. This comprises external walls between 400mm and 600mm thick with two 650mm thick internal walls supporting the Pivot Bearing. A 1350mm thick concrete slab then supports the lifting cylinder and a number of high-level slabs on foam concrete to provide a plant room area, capped by a sloped approach slab to the bascule bridge.

The Marine Causeway structure adjacent to this runs alongside the existing marine deck structure of the Wood Wharf development, consisting of bored marine piles supporting transverse precast beams at typically 5400mm centres. Precast planks then span between the beams providing permanent formwork and acting compositely with the insitu slab, with an overall slab depth of 400mm. Precast parapet units run along the length of the causeway supported on the transverse beams with discrete shear keys cast into the concrete slab.

Kilnbridge were appointed by Canary Wharf Contractors Ltd to construct the concrete structures for both of the Abutments and the Marine Causeway, as well as developing the methodology and temporary works for the project, on a fixed price lump sum contract.

Planning of the detailing for the marine causeway was driven by the lifting capacity of the crawler crane to be utilised for the project, requiring Kilnbridge to change the design of the finished edge parapet units to a twin wall style system with an infill strip to enable ease of lifting and construction. Further complexity was added with the detailing required for the East Abutment structure, which was to be constructed above the water level before being lowered into place and then completed, with a number of temporary reinforcing bars to suit the change in the structural loading.

What were the challenges and what made the project successful.

The finished product of the Marine Causeway and East Abutment, seen within the submitted images, provides an understated and simple appearance, but the bespoke structural details and construction techniques involved belie this. By combining techniques from across the industry, a construction solution was developed that fulfilled and often exceeded the client's requirements ensuring safe and efficient working throughout the project. Careful planning and trials ensured the success of the novel solutions employed for the project and delivery of the challenging project, with complex reinforcing and concrete interfaces.

The challenges overcome and solution have been recognised by the industry through the award of the British Construction Industry Temporary Works Initiative of the Year (Civil Engineering) Award 2018, commendation for the CONSTRUCT Project of the Year (over £2.5million) Award 2018 and short listing for Construction News Project of the Year by a Specialist Contractor (£3million to £5million) Award, with the latter yet to be awarded.

Ensuring that a tight programme could be achieved with a limited three month pre-construction lead-in period requiring accelerated design and detailing for the precast elements that could be co-ordinated with the insitu elements to follow. The success of this ensured that the project was delivered ahead of the key hard deadline for the bascule bridge installation and within budget despite the technical challenges and bespoke nature of the project.

What benefits utilizing BIM and Tekla Software brought to the project.

Given the hybrid nature of the structure, combining insitu concrete, precast concrete, finished concrete and temporary works elements, co-ordination and development of the solution within the limited time frame was aided immeasurably by the use of BIM and notably Tekla. An animation of the construction programme based on the model was produced to provide a visual tool for the operatives during the inductions and site briefings to ensure that all were aware of the sequence of works and key deliverables.

The production capabilities and the ease of change control allowed within Tekla was exemplified when only two weeks prior to a key element of the works being constructed, the permanent works engineer realised that they had not correctly accounted for the loading from a ship impact and required substantial changes in the reinforcement. This was incorporated within the model, clash checked and the corresponding drawings and schedules generated within only two days to enable a short approval period for reinforcement to be delivered to site on time and the maximum re-use of previously ordered reinforcement from the now defunct design. This enabled us to achieve our deadline for the lowering of the East Abutment structure and did not impact the overall construction programme.

In addition to this, all structural steelwork for the temporary works was model, detailed and scheduled from Tekla by our fabrication department also enabling a comparison of geometry for the clash detection prior to installation.

The project in numbers

Length of Marine Causeway - 110m. Reinforcement Tonnage - Circa. 300 Tonnes.

Tekla BIM Awards

The Tekla BIM Awards honor projects that transform the way the world builds.

See all projects

The Content on this page is provided to Trimble Solutions Corporation ("Trimble") under the Tekla BIM Awards Terms and Conditions.

Trimble Logo

UK (ENGLISH)

globe wireframe
magnifying glass
Tekla logo

Productscaret icon

Tekla Structures skip iconTekla Model Sharing skip iconTekla PowerFab skip iconTekla Tedds skip iconTekla Structural Designer skip iconTekla Portal Frame Designer & Tekla Connection Designer skip iconTrimble Connect skip iconAll products skip icon

Solutions downward-facing caret

Designright caret

Constructible modeling skip iconConceptual design skip iconStructural analysis & design skip iconDesign communication skip iconConnected design skip icon

Detailright caret

Constructible detailing skip iconConstruction documentation skip icon

Fabricateright caret

Production planning & management skip iconAutomated production skip iconConnected project delivery skip icon

Constructright caret

Bid & win skip iconSite planning & coordination skip iconConnected worksite skip icon

Educateright caret

Tekla Campus skip iconTekla for students skip iconTekla for educators skip iconTekla for academic institutions skip icon

All solutions

Resourcescaret icon

Articles & blog posts skip iconReferences skip iconWebinars skip iconeBooks skip iconNews skip iconEvents skip iconTekla BIM Awards skip iconThe jobs board skip iconAll resources skip icon

Supportcaret icon

Trimble Downloads skip iconTekla Discussion Forum skip iconTekla User Assistance skip iconTekla Warehouse skip iconTekla Developer Center skip iconTraining skip iconAll support skip icon

Aboutcaret icon

Why Tekla & Trimble skip iconContact us skip iconCareers skip iconTekla Trust Center skip iconLicense compliance skip iconAll about skip icon

| UK (ENGLISH)

globe wireframe icon

Productscaret icon

  • Tekla Structures
  • Tekla Model Sharing
  • Tekla PowerFab
  • Tekla Tedds
  • Tekla Structural Designer
  • Tekla Portal Frame Designer & Tekla Connection Designer
  • Trimble Connect
  • All products

Solutionscaret icon

Designcaret icon

  • Constructible modeling
  • Conceptual design
  • Structural analysis & design
  • Design communication
  • Connected design

Detailcaret icon

  • Constructible detailing
  • Construction documentation

Fabricatecaret icon

  • Production planning & management
  • Automated production
  • Connected project delivery

Constructcaret icon

  • Bid & win
  • Site planning & coordination
  • Connected worksite

Educatecaret icon

  • Tekla Campus
  • Tekla for students
  • Tekla for educators
  • Tekla for academic institutions
All solutions

Resourcescaret icon

  • Articles & blog posts
  • References
  • Webinars
  • eBooks
  • News
  • Events
  • Tekla BIM Awards
  • The jobs board
  • All resources

Supportcaret icon

  • Trimble Downloads
  • Tekla Discussion Forum
  • Tekla User Assistance
  • Tekla Warehouse
  • Tekla Developer Center
  • Training
  • All support

Aboutcaret icon

  • Why Tekla & Trimble
  • Contact us
  • Careers
  • Tekla Trust Center
  • License compliance
  • All about
  1. Home
  2. Tekla BIM Awards
  3. Water Street Bridge
CONTACT US