not-allowed-link

Luton DART Stations

Winner icon
Public Projects Winner

About the project

Project category

Public projects

Company / Project parties

Hewson Consulting Engineers

Location

United Kingdom

Images

placeholder imageplay button

Luton DART Stations

The Project is the Luton DART (Direct Air-Rail Transit), a new light rail link between Luton Airport Parkway mainline railway station and the airport terminal.

Once completed, the DART will be a driverless system providing transit along the 2.1km route, with the journey time from the station to the terminal, or vice versa, taking approximately five minutes to complete. At present, this connection is serviced by a shuttle bus, with service reliability and journey time heavily affected by traffic congestion. The DART will avoid the need for such a shuttle bus service, providing a more direct and reliable connection therefore reducing stress to passengers and improving their experience.

Hewson are structural designers for the two stations on the DART, working within a wider design team for the D&B contractor Volker-Fitzpatrick Kier JV (VFK JV).

Parkway station is a two-story building providing connectivity between the DART and the surrounding area, including a direct link to the existing railway station. DART trains arrive via a viaduct structure with platforms and concourse area on the first floor, and vertical circulation providing transit to ground floor. Drive systems for the cable-pulled trains are housed at ground level below the concourse area.

Central Terminal station is a underground station within the airport terminal, with rail access via a new adjoining cut and cover tunnel. From platform level approximately 10m below ground, passengers will transfer to ground level and directly into the terminal building. The underground structure also houses a train maintenance facility, past the platforms, for train wash down and servicing, as well as back of house rooms and facilities.

Both stations were modelled in Tekla Structures, including all concrete, reinforcement and steelwork. Larger elements of temporary works, also designed by Hewson, were included within the same model in order to ensure compatibility with the permanent works and to aid communication of design and construction intent.

Construction of the DART civil structures is well underway, with a target opening date of 2021.

What were the challenges and what made the project successful?

As is typical for Design & Build projects, the programme provided a key challenge for design and construction of the DART system including the two stations at either end. Detailed design submissions and approvals were thus phased to conform with the intended construction programme.

At Parkway station the close proximity of the existing railway station and tracks formed a key constraint, whilst within the airport terminal itself the space available for construction of the Central Terminal station deep basement was particularly limited. The footprint of Central Terminal Station passes below an existing airport footbridge, requiring its intermediate piers to be underpinned and their piled foundations removed as part of the works, with a new load path constructed below using the new station structure. This required careful sequencing and control, as well as closely-integrated permanent and temporary works (both included within the same Tekla Structures model).

What benefits did utilizing BIM and Tekla software bring to the project?

The benefits of using Tekla have been numerous. Early in the project we pushed for IFC model transfers to ensure interoperability between each discipline’s models, which were created in a variety of programmes (including Revit, Civils 3D, Tekla). Tekla BIMSight was a key tool in getting buy-in to this, due to it being free to everyone on the project and easily accessible with its simple user-interface and ability to quickly combine numerous models. This was a very helpful way to federate models ‘informally’, in addition to the formal project Common Data Environment.

Reinforcement detailing within the model has hugely improved buildability – we identified potentially congested areas of reinforcement early on and modelled options which we discussed with the contractor, so that we could incorporate preferred solutions first time around. TQs related to reinforcement have therefore been extremely rare, since the reinforcement has been ‘constructed’ virtually within the design phase, and the IFC export of the reinforcement has become a valuable tool for the site team, which we provided over and above our contractually required deliverables. The contractor has noted that not a single bar bending schedule error has occurred, which is a direct result of the reinforcement being scheduled automatically within Tekla Structures.

With such large structures, model sharing has also been invaluable for the model production – with up to six or seven people working on different parts of each station at any one time, across three companies. We have found the model sharing tool to be extremely reliable and efficient, and looking back it is hard to see how the models could have been completed on time, to the required level of detail and quality, without this feature.

As the project has progressed, VFK have increased Hewson’s scope to include numerous secondary items, including curtain wall steelwork and roof purlins. Tekla’s ability to model these smaller items, as well as the larger heavy civils, has meant that we can maintain a single model including all structural elements. Custom connection components and Kingspan modules have been particularly helpful features in these latter stages.

 

The project in numbers

Total cost of the DART project is c. £225m of which the civils component is c. £120m and the stations combined are c. £50m.

 

Parkway Station:

  • Length & width = 140m long x 23m wide x 15m high (excluding piles)
  • Structural concrete = 12,000 tonne (approx)
  • Reinforcement = 900 tonne (approx)
  • Structural steel = 820 tonne (approx)

Central Terminal Station:

  • Length & width = 200m long x 24m wide x 22m high (top of roof to soffit of base slab)
  • Structural concrete = 30,000 tonne (approx)
  • Reinforcement = 1500 tonne (approx)
  • Structural steel = 840 tonne (approx)

Tekla BIM Awards

The Tekla BIM Awards honor projects that transform the way the world builds.

See all projects

The Content on this page is provided to Trimble Solutions Corporation ("Trimble") under the Tekla BIM Awards Terms and Conditions.

Trimble Logo

UK (ENGLISH)

globe wireframe
magnifying glass
Tekla logo

Productscaret icon

Tekla Structures skip iconTekla Model Sharing skip iconTekla PowerFab skip iconTekla Tedds skip iconTekla Structural Designer skip iconTekla Portal Frame Designer & Tekla Connection Designer skip iconTrimble Connect skip iconAll products skip icon

Solutions downward-facing caret

Designright caret

Constructible modeling skip iconConceptual design skip iconStructural analysis & design skip iconDesign communication skip iconConnected design skip icon

Detailright caret

Constructible detailing skip iconConstruction documentation skip icon

Fabricateright caret

Production planning & management skip iconAutomated production skip iconConnected project delivery skip icon

Constructright caret

Bid & win skip iconSite planning & coordination skip iconConnected worksite skip icon

Educateright caret

Tekla Campus skip iconTekla for students skip iconTekla for educators skip iconTekla for academic institutions skip icon

All solutions

Resourcescaret icon

Articles & blog posts skip iconReferences skip iconWebinars skip iconeBooks skip iconNews skip iconEvents skip iconTekla BIM Awards skip iconThe jobs board skip iconAll resources skip icon

Supportcaret icon

Trimble Downloads skip iconTekla Discussion Forum skip iconTekla User Assistance skip iconTekla Warehouse skip iconTekla Developer Center skip iconTraining skip iconAll support skip icon

Aboutcaret icon

Why Tekla & Trimble skip iconContact us skip iconCareers skip iconTekla Trust Center skip iconLicense compliance skip iconAll about skip icon

| UK (ENGLISH)

globe wireframe icon

Productscaret icon

  • Tekla Structures
  • Tekla Model Sharing
  • Tekla PowerFab
  • Tekla Tedds
  • Tekla Structural Designer
  • Tekla Portal Frame Designer & Tekla Connection Designer
  • Trimble Connect
  • All products

Solutionscaret icon

Designcaret icon

  • Constructible modeling
  • Conceptual design
  • Structural analysis & design
  • Design communication
  • Connected design

Detailcaret icon

  • Constructible detailing
  • Construction documentation

Fabricatecaret icon

  • Production planning & management
  • Automated production
  • Connected project delivery

Constructcaret icon

  • Bid & win
  • Site planning & coordination
  • Connected worksite

Educatecaret icon

  • Tekla Campus
  • Tekla for students
  • Tekla for educators
  • Tekla for academic institutions
All solutions

Resourcescaret icon

  • Articles & blog posts
  • References
  • Webinars
  • eBooks
  • News
  • Events
  • Tekla BIM Awards
  • The jobs board
  • All resources

Supportcaret icon

  • Trimble Downloads
  • Tekla Discussion Forum
  • Tekla User Assistance
  • Tekla Warehouse
  • Tekla Developer Center
  • Training
  • All support

Aboutcaret icon

  • Why Tekla & Trimble
  • Contact us
  • Careers
  • Tekla Trust Center
  • License compliance
  • All about
  1. Home
  2. Tekla BIM Awards
  3. Luton DART Stations
CONTACT US