not-allowed-link

Gatwick Airport Station Upgrade

"This project was complex and there was high attention to detail, using DfMA to ensure that the construction process went smoothly. This was a very impressive project with full model coordination and collaborative working." - Judges' comments

Winner icon
Infrastructure projects winner

About the project

Project category

Infrastructure

Company

Kilnbridge Construction Services Limited

Location

Gatwick, UK

Other parties

Network Rail, Gatwick Airport Ltd, Costain, Systra

Gallery

placeholder imageplay button

Model flythrough

Site progress reporting in Trimble Connect

Complex assemblies

Modelling of glass balustrades

Photo of concourse

Photo of plane landing behind concourse

Services routes integration

Incorporating stairs into model

Project in numbers

Assemblies fabricated

13,200 approx.

Bolts used

49,300 approx.

Trimble products used

Tekla Structures, Tekla Model Sharing, Trimble Connect

Keeping the trains running at the Gatwick Airport Station upgrade

The Gatwick Airport Station upgrade was undertaken to improve the facilities within the station, specifically addressing issues with overcrowding and to improve the passenger experience, while also ensuring additional capacity for future growth. It was a critical requirement for the project to try and deliver these works while maintaining near normal operations for the passengers using the station.

One of the key components of the Gatwick Airport Station upgrade was the expansion of the existing concourse, which had to be built over the top of four existing live tracks and platforms. This required the maximising of all DfMA opportunities, extensive advance coordination with MEPH and Finishes, while also ensuring full integration with existing structures and services.

Kilnbridge Construction Services were tasked with delivering three structures within the scope of works, collaborating with Costain, Systra, Emico and others to deliver the project successfully.

 

Challenges and achievements

The challenges on the Gatwick Airport Station upgrade project were extensive and ranged from practical, to access, to geometrical. The main overarching challenge was the severe spatial constraints on the project, meaning that virtually every component had to arrive on the project for direct installation.

There was very little opportunity for retrofit work to take place once installed, due to the operational railway. In practice, this meant that Kilnbridge Construction Services needed to maximise the amount of work completed on all components off site through a number of ways:

  • Ensuring exact build sequence management.
  • Extensive coordination and allowance for cladding and MEPH support structures and penetrations, to ensure they were fully integrated at design stage.
  • Development and integration of connections and interfaces with all balustrades and glazing by third parties.
  • Developing highly loaded connection designs that delivered on structural and security requirements while also meeting both the architectural and spatial requirements whether they remained visible or interfaced with the cladding finishes.

The above challenges were further exacerbated by the arrival of COVID. With all parties working remotely, IFCs, clash detection and Trimble Connect became absolutely critical tools to enable development, coordination and communication of the design challenges that had to be overcome.

Developing the buildability of what was a large and challenging structure with complex connections, geometry and interfaces, and then for that to later lead to successfully delivering the project in the most complex of environments is a challenge worthy of celebration.

 

Using Tekla software

  • The majority of profiling, cutting and drilling was undertaken by specialist suppliers with full CNC operating systems. They were provided with both the NC and PDF files for each component, exported directly from Tekla Structures.
     
  • In order to maximise DfMA targets and minimise work on site, once assemblies were initially developed and modelled, IFCs for the individual assemblies were used to assess transportation constraints. This included swept path analysis, and also to review crane lifting operations to ensure weights and size were compatible with site restrictions. Many times this review process triggered a change to the design that proved critical later on site.
     
  • “Marked Category” was used to create additional sub-phases that allowed better management of the process of issuing components to manufacture. This also helped where certain parts of a work phase could not be issued due to an ongoing design change, for example, ensuring additional sub phasing was possible to better track these components.
     
  • Proposed connections would first be modelled in Tekla and then the files exported to the connection design software where calculations would be run and further development of the connections undertaken. This process ensured the practical requirements were understood from an installation perspective by the structural engineer, thereby ensuring an element of autonomy for them to develop the final calculations or make amendments with a high degree of confidence that no rework would be required.
     
  • Due to the complexity of the connection and loading arrangements, IDEA StatiCa was utilised to develop the connection design. The process for communicating any updated connection design from IDEA StatiCa to Tekla followed a more traditional approach in that, the connection design report was issued to the detailers along with the updated connection model from IDEA StatiCa and changes were subsequently updated directly by the detailer within the main Tekla Structures model.
     
  • Changes communicated by the design team would be incorporated into Kilnbridge Construction Services’s Tekla model and would then be reviewed as part of a regular model exchange process, to ensure that any updates would not cause any secondary clashes or impacts as a result.

 

What does Kilnbridge Construction Services Limited say about the project?

“Over the last number of years, we have always had the goal of having a Steel Structures entry into the Tekla awards, but we also felt it needed to be the right project and we believe this one is. Steelwork detailers normally operate in the background of every construction project and are rarely if ever exposed to the external appreciation or plaudits that the more visible construction roles are. They provide a critical role in the planning, Health and Safety, construction methodology development, as it is in this design phase of the project that the majority of those decisions are made and on this project alone, our detailers were responsible for identifying and flagging numerous emerging issues during the model development that may otherwise have gone unnoticed and proved costly later in the project. The Tekla Awards provide a unique opportunity not only for the companies who undertake these projects to be recognised, but just as importantly, to acknowledge specifically, the invaluable contribution made by the individuals involved in design and detailing roles by giving us a platform to promote their achievements.

The continued development of Tekla meant that in recent years its increased versatility and capabilities has meant that virtually all our detailing responsibilities for our works can be delivered within one software package (Tekla) meaning we have been able to more effectively coordinate not only our own works, but with other interfacing contractors on our projects. This capability to incorporate such a diverse range of work into one model has allowed us to not only streamline our design process but also to better support our client with their coordination also.” 

          - Terry Murphy, Technical Director at Kilnbridge Construction Services Limited

UK Tekla Awards

The UK Tekla Awards honour projects that transform the way the world builds.

See all projects

The Content on this page is provided to Trimble Solutions Corporation ("Trimble") under the Tekla BIM Awards Terms and Conditions.

Trimble Logo

UK (ENGLISH)

globe wireframe
magnifying glass
Tekla logo

Productscaret icon

Tekla Structures skip iconTekla Model Sharing skip iconTekla PowerFab skip iconTekla Tedds skip iconTekla Structural Designer skip iconTekla Portal Frame Designer & Tekla Connection Designer skip iconTrimble Connect skip iconAll products skip icon

Solutions downward-facing caret

Designright caret

Constructible modeling skip iconConceptual design skip iconStructural analysis & design skip iconDesign communication skip iconConnected design skip icon

Detailright caret

Constructible detailing skip iconConstruction documentation skip icon

Fabricateright caret

Production planning & management skip iconAutomated production skip iconConnected project delivery skip icon

Constructright caret

Bid & win skip iconSite planning & coordination skip iconConnected worksite skip icon

Educateright caret

Tekla Campus skip iconTekla for students skip iconTekla for educators skip iconTekla for academic institutions skip icon

All solutions

Resourcescaret icon

Articles & blog posts skip iconReferences skip iconWebinars skip iconeBooks skip iconNews skip iconEvents skip iconTekla BIM Awards skip iconThe jobs board skip iconAll resources skip icon

Supportcaret icon

Trimble Downloads skip iconTekla Discussion Forum skip iconTekla User Assistance skip iconTekla Warehouse skip iconTekla Developer Center skip iconTraining skip iconAll support skip icon

Aboutcaret icon

Why Tekla & Trimble skip iconContact us skip iconCareers skip iconTekla Trust Center skip iconLicense compliance skip iconAll about skip icon

| UK (ENGLISH)

globe wireframe icon

Productscaret icon

  • Tekla Structures
  • Tekla Model Sharing
  • Tekla PowerFab
  • Tekla Tedds
  • Tekla Structural Designer
  • Tekla Portal Frame Designer & Tekla Connection Designer
  • Trimble Connect
  • All products

Solutionscaret icon

Designcaret icon

  • Constructible modeling
  • Conceptual design
  • Structural analysis & design
  • Design communication
  • Connected design

Detailcaret icon

  • Constructible detailing
  • Construction documentation

Fabricatecaret icon

  • Production planning & management
  • Automated production
  • Connected project delivery

Constructcaret icon

  • Bid & win
  • Site planning & coordination
  • Connected worksite

Educatecaret icon

  • Tekla Campus
  • Tekla for students
  • Tekla for educators
  • Tekla for academic institutions
All solutions

Resourcescaret icon

  • Articles & blog posts
  • References
  • Webinars
  • eBooks
  • News
  • Events
  • Tekla BIM Awards
  • The jobs board
  • All resources

Supportcaret icon

  • Trimble Downloads
  • Tekla Discussion Forum
  • Tekla User Assistance
  • Tekla Warehouse
  • Tekla Developer Center
  • Training
  • All support

Aboutcaret icon

  • Why Tekla & Trimble
  • Contact us
  • Careers
  • Tekla Trust Center
  • License compliance
  • All about
  1. Home
  2. Tekla BIM Awards
  3. Gatwick Airport Station Upgrade
CONTACT US