Cemex Climafuel Store Building

A large single span processing plant for Cemex. Sequencing utilized to ensure a smooth erection programme. BIM helped integrate 3D models and run clash checks.

About the project

Project category

Industrial

Company / Project parties

Robinson Structures

Location

United Kingdom

Project in numbers

Cost

£3 million

Length

78 m

Number of pre-cast concrete panels

192

Height

21 m

Trimble products used

Tekla Structures, Trimble Connect, Tekla Model Sharing

Images

placeholder imageplay button

Cemex Climafuel store building

A large single span processing plant for Cemex at Rugby. The new building enables Cemex to expand their facilities for the production of concrete materials and also supplies them with a new storage building.

  • The building consists of a single span braced steel building with roof trusses, multiple floor levels, cranes & basements.
  • The building is approximately 32m in span and 21m high to eaves from the lowest level.
  • Some of the columns are supported on concrete walls at a raised level whilst others are supported on concrete pad footings.
  • There are multiple mezzanine floors to one of end of the building and a smaller canopy area to the opposite end. The canopy is full width of the building and approximately 14m to eaves.
  • The building is stabilised utilising vertical and roof bracing. There is also bracing to the lower chord of the roof trusses.
  • The main part of the building is divided in two along its length by a dividing concrete wall with steel sheeted wall above. Each side of the building has an overhead crane running along the length.

What were the challenges and what made the project successful?

This prestigious project was a highly complex structure, multi-level design to accommodate various plant and machinery as well as an extensive truss structure to create an open space within the storage area of the building.

All aspects of the project from the main steel through to stairs, handrails, mesh and chequer plate flooring were completed in sequence utilising both in-house and external drawing offices through model sharing.

As part of Robinson Structures work there was a requirement to lift the hoppers, and conveyor machinery into place during the course of the steel frame erection, this entailed a tightly sequenced steel erection programme for this scheme to ensure that the main structure and secondary steelwork was at the correct stage for this to happen working alongside Cemex sub-contractors. The use of client BIM models for the plant uploaded to the steel frame model was invaluable in completing this activity.

What benefits did utilizing BIM and Tekla software bring to the project?


The detailing programme was as orderly sequenced as the erection phase to ensure that the main structure, secondary steel and the pre-cast concrete panels were issued in the correct sequence to ensure a smooth erection programme with a total of over 70 nr deliveries required to co-ordinate. We collaborated closely with Cemex sub-contractors utilising BIM methods by integrating the 3d models of the various hoppers and machinery into our steelwork model to run clash checks and help coordinate the works.
Utilising the Tekla Structures model sharing platform enabled Robinsons to work on the different aspects of this project whilst achieving the detailing programme.

Our contract department used Tekla Trimble Connect software to establish an erection sequence and this then allowed our site manager to keep track of the project progression during the erection programme phase and check installation details of complex connections.

 

The project in numbers

  • Cost £3m (approx)
  • 32m span x 78m long x 21m high
  • 700t (approx)
  • 192 Pre-Cast Concrete Panels
  • 1250m of Handrailing

Tekla BIM Awards

The Tekla BIM Awards honor projects that transform the way the world builds.

See all projects

The Content on this page is provided to Trimble Solutions Corporation ("Trimble") under the Tekla Global BIM Awards Terms and Conditions.

Trimble Logo

INTERNATIONAL (ENGLISH)

globe wireframe
magnifying glass
Tekla logo

Productscaret icon

Tekla Structures skip iconTekla Model Sharing skip iconTekla Structural Designer skip iconTekla Tedds skip iconTekla PowerFab skip iconTrimble Connect skip iconAll products skip icon

Solutions downward-facing caret

Designright caret

Constructible modeling skip iconConceptual design skip iconStructural analysis & design skip iconDesign communication skip iconConnected design skip icon

Detailright caret

Constructible detailing skip iconConstruction documentation skip icon

Fabricateright caret

Production planning & management skip iconAutomated production skip iconConnected project delivery skip icon

Constructright caret

Bid & win skip iconSite planning & coordination skip iconConnected worksite skip icon

Educateright caret

Tekla Campus skip iconTekla for students skip iconTekla for educators skip iconTekla for academic institutions skip iconTrimble student ambassador program skip icon

All solutions

Resourcescaret icon

Articles & blog posts skip iconReferences skip iconWebinars skip iconNews skip iconEvents skip iconeBooks skip iconTekla BIM Awards skip iconAll resources skip icon

Supportcaret icon

Tekla User Assistance skip iconTrimble Downloads skip iconTekla Discussion Forum skip iconTekla Warehouse skip iconTekla Developer Center skip iconTraining skip iconAll support skip icon

Aboutcaret icon

Why Tekla & Trimble skip iconContact us skip iconCareers skip iconTekla Trust Center skip iconLicense compliance skip iconAll about skip icon

| INTERNATIONAL (ENGLISH)

globe wireframe icon

Productscaret icon

  • Tekla Structures
  • Tekla Model Sharing
  • Tekla Structural Designer
  • Tekla Tedds
  • Tekla PowerFab
  • Trimble Connect
  • All products

Solutionscaret icon

Designcaret icon

  • Constructible modeling
  • Conceptual design
  • Structural analysis & design
  • Design communication
  • Connected design

Detailcaret icon

  • Constructible detailing
  • Construction documentation

Fabricatecaret icon

  • Production planning & management
  • Automated production
  • Connected project delivery

Constructcaret icon

  • Bid & win
  • Site planning & coordination
  • Connected worksite

Educatecaret icon

  • Tekla Campus
  • Tekla for students
  • Tekla for educators
  • Tekla for academic institutions
  • Trimble student ambassador program
All solutions

Resourcescaret icon

  • Articles & blog posts
  • References
  • Webinars
  • News
  • Events
  • eBooks
  • Tekla BIM Awards
  • All resources

Supportcaret icon

  • Tekla User Assistance
  • Trimble Downloads
  • Tekla Discussion Forum
  • Tekla Warehouse
  • Tekla Developer Center
  • Training
  • All support

Aboutcaret icon

  • Why Tekla & Trimble
  • Contact us
  • Careers
  • Tekla Trust Center
  • License compliance
  • All about
  1. Home
  2. Tekla BIM Awards
  3. Cemex Climafuel store building
CONTACT US