BIM-Enabled Real-Time Supply Chain Management at DPR Construction, Inc. using Tekla Structures and Vela Systems
The System
During construction of the UCSC Porter B College, DPR Construction, Inc. used field mobility software, tablet computers and Building Information Modeling to manage all aspects of their Door, Frame and Hardware (DFH) process.
The usual DFH workflow involves tracking progress of doors and
hardware receipt, quality inspection and installation by making notes
on paper logs and drawings and then spending hours explaining, fixing
and manually updating printed progress reports.
DPR Construction chose to replace this traditional workflow with a process that is centered on Building Information Modeling and material tracking using construction field software. Prior to construction, the facility and the doors and frames were modeled in 3D using Tekla Structures.
This information was integrated into the Vela Systems field software Materials Tracker product. As each door assembly arrived on site, preprinted barcodes were attached and scanned using Vela Systems installed on Tablet PCs with integrated barcode scanners. The barcodes were scanned at various stages during the installation process (e.g., received, installed, etc).
Status information was synchronized from Vela Systems to the Tekla Structures Building Information Model (BIM) either from the office or the field.
In Tekla Structures, each component’s status could be monitored visually, and the model could be colorized to show its status.
The Benefits
As a part of a research project affiliated with the Center for Integrated Facility Engineering (CIFE) at Stanford University, a detailed study was done of the implementation and benefits of utilizing this system. Three key benefit areas were identified and expand below.
1. Time Savings
“With the old process, I had to fax huge amounts of paper work (e.g., fax door IDs) and make countless numbers of calls for status updates. We have gained substantial time savings with the new system.” - Darrin Sterlinski, DFH Foreman, UCSC Porter B Project
The research found that using the integrated system DPR realized a time savings of between 50% and 80% (depending on task) for DFH tasks. More than 28 hours of time were saved in recording, documentation, communication, and reporting. The time savings came from faster processes, removal of steps, and faster information flow. The researchers found that 5 steps were removed in each phase of receipt + QA/QC inspection, installation + QA/QC inspection, and final walkthrough for DFH.
2. Clear Progress Visibility
“With the integrated system we moved from saying ‘We think we are 75% complete’ to saying ‘We know exactly which 75% is actually complete.’” - Lisa Thomas, Manager, DPR DFH Division
Using Tekla Structures web-based Building Information Model, DPR was able to publish the 3D model to their project website. With the regular updates from the field through the Vela Systems software, this web-based model could be updated in real-time. Daily, crews could see in 3D what the current status of each component was and thus what needed to be completed next in the sequence. Not only saving time, it also permitted DPR to calculate accurate progress reports and manpower statistics.
As another benefit, the progress visibility was used to gain a better understanding of the productivity of the team members over time.
“On this project, we were able to have an accurate picture of what can actually be installed with the number of people on the project. This helps for future planning.” - Lisa Thomas, Manager, DPR DFH Division
3. Reorder Rate Reduction
Typically, a portion of any reorder of material is unnecessary and a clear financial loss to the project. The Tekla Structures/Vela Systems solution improved visibility into the availability of openings (e.g. ordered, onsite, damaged, installed) such that zero reorders were needed for the project, translating into direct financial benefit to the project. By making information immediately available to the DFH foreman in the field at the point of construction in Vela Systems, better decisions were made about what and when to reorder. Not only did a 3D view of the project provide immediate insight into reorder requirements, but it also provided a high level of assurance and accountability.
Conclusion
Like most jobsite material management processes today, traditional DFH workflows involve tedious paperwork, frequent phone calls/ faxes and challenging coordination. DPR Construction, Inc. used Tekla Structures and Vela Systems Field Mobility Software to implement a visual, automated and connected solution that brought efficiency and accountability to the process. Whether tracking DFH or any other critical path material, equipment, or components, integrated solutions of BIM and Field Software are streamlining construction industry.
supply chain management.