钢结构模型 

 

Advanced Candu Reactor, CanadaVote

Atomic Energy of Canada Limited

Comprehensive concrete module
The term module can be defined as an assembly comprised of structural steel, pipe supports, process piping & equipment, instrumentation, cable trays, panels, embedments, rebar, etc. within a defined volume. Models can be prefabricated either off-site or at an on-site fabrication facility and installed in the field. Constructing with the module concept allows fabrication of many modules to take place as parallel activities, shortening the overall construction schedule while fabricating in a controlled environment. This particular example represents a Prefabricated Permanent Formwork (PPF) Multi-Discipline Module. Which translates to a module consisting of process piping & equipment, steel wall plates, embedments, temporary steel, rebar, etc. The plate work that makes up the walls act as the formwork and remains in place after the concrete has cured.

Passing on the model downstream
This project is still in the preliminary stage and has not passed anything out for fabrication yet. However, AECL is working closely with fabricators/detailers to develop standards that will be used to build on when information starts to flow between all parties. The BIM process will allow AECL to pass a 3D model from their design team to contractors, detailers, fabricators, etc. each adding their own additional details to the original design model. The result should greatly increase the quality of the model and reduce the information loss when the model is passed between disciplines.

ALDAR HQ, Middle EastVote

William Hare

Middle East's first spherical building
ALDAR's new headquarters is the first spherical building in the Middle East, standing approximately 110m in height with 23 floor levels. The building has a diameter of 120.9m; its width varies from 10m at ends to 36.4m in the middle. The structural design has a central concrete core for transferring environmental lateral loads with peripheral diagrid support columns forming the building’s envelope. The building requires 6400 ton of steel; 55,000m2 of decking panels, and 25,000m3 of concrete and has an area of glass of 25,000m2 (3200 panels of glass). The building will have a total gross floor area of 61,900m2 and a total net area of 51,361m2.The building includes many complicated elements, such as peripheral diagrid columns, outer ring, internal ring, central ring columns, diagrid nodes, and in plane truss connecting the outer, internal and central columns at all floor levels. The roof is an integral part having primary beams in line with the columns.

Engineering and model data used at the earliest stages
William Hare Engineering utilizes computer aided design and detailing using Tekla software to develop client’s designs, maximize efficiency and to engineer practical solutions for its manufacturing facilities. Engineering and model data were used at the earliest stages of the project to take full advantage of early procurement and optimized material utilization. In engineering a time saving of 5% is achieved while utilizing the architect’s or consultant’s model with no increase in accuracy. If they would have had to use 2D information on follow-on trades, it would have added another 20% to the detailing of the project. In the fabrication the Tekla drawing details were used seamlessly with in-house fabrication data package, such as for producing NC files for use with CNC machines and bill of material data manipulation. During erection the drawings and reports along with the Tekla Web Viewer models were utilized for more accurateness.

Back to top

Artwork Sirocco, FinlandVote

A-Insinöörit Suunnittelu Oy

430 aluminum profiles
Sirocco is work of art located in the Arabianranta housing area in Helsinki. It was designed by Kivi Sotamaa of Sotamaa Design and consists of 430 aluminum profiles, the length of which varies from 1,15 to 4,45 meters. All connections were modeled by using Tekla Structures’s custom components. The lower end of the artwork is connected to pad footings, and its profiles are supported by plywood plates during the construction phase.

Direct data transfer from the model to analysis and fabrication
Finnish engineering office A-Insinöörit Suunnittelu Oy used Tekla Structures version 15.0 for the structural design of the project. Architect design was done by Maya Unlimited and Rhinceros 4.0, and that information was exported to Tekla Structures in 3D DWG format. The places of profiles were delivered to measuring devices directly from Tekla Structures. The data for the plywood supports and aluminum profiles were exported from the Tekla model directly to CNC-machines.

Back to top

Capital Gate, Middle EastVote

Eversendai

World’s most inclined building
Capital Gate is a 35-storey illustrious iconic tower, 525 feet tall, a part of the Capital Center development around Abu Dhabi National Exhibition Center. It features a presidential-style luxury hotel and office spaces. Leaning towards one direction in an angle of about 18 degrees, the tower has been nominated for the Guinness Book of World Records as the world’s most inclined building. The structure features a cantilevered internal atrium at 17th and 18th floors to accommodate the facilities of the projecting swimming pool and tea lounge. Diagrid technology has been adopted in the construction of the structure. Each diamond of the external cladding is supported by the steel diagrid panel. To maintain the required curved surface profile, every panel surface is slightly deviating with respect to the adjacent panel surfaces. External diagrid members are of rectangular hollow tubes whereas the internal diagrid members are of circular hollow pipes. External diagrid members provide secondary supports for the wave-shape ‘Splash’ structure from 19th level down to the bottom, providing an aesthetic sun shade to the tower. Main structural steel work has consumed more than 13,000 tons of material in addition to the metal decking. Steel skeleton consists of 707 external diagrid nodes and 20 internal diagrid nodes at the intersection of the members. At the intersecting nodal points, the hollow members have met with offsets in all three axes along their surfaces. As none of the panels is coplanar to the other, each node is unique on its own and formed with heavy thick cruciform punchthrough plates. In order to minimize the member offsets at the nodal points, diagrid members are oriented by using the method of ‘bisection of bisecting planes’.

Faster and safer completion by BIM
Complexity in modeling the diagrid members was well managed with the features of Tekla Structures. The Tekla attributes helped in all fronts for a smooth construction of the structure. Concerning design, members were oriented with minimal offset by adopting the method of bisection of bisecting planes. These offset values were taken from the 3D model and used in the design of cruciform nodes. Available length of weld was taken from the model to do the weld design of cruciform nodes. Beams connected to the nodes were moved in the 3D model to avoid member clashing which resulted in eccentric connections. The eccentricity was measured from the model and used in the connection design. From the preliminary model developed at the initial stage of the project actual cut-to-length of the members was taken to procure the material. This helped in reducing material wastage. Quantity of bolts, shear studs and paint was obtained from the Tekla Structures reports. Assembly lists derived from the Tekla model were converted into worksheets. Other departmental activities, like fabrication, painting and erection, were planned and monitored using these worksheets. The NC files exported from the model facilitated faster and accurate fabrication. Temporary jigs were made with the help of the coordinates of individual assemblies that were taken from the model. Fit up of the individual parts of the nodes wasdone with the 3D coordinates taken from the model. Location of center of gravity and weight of individual assembly were taken from the reports. These were used to work out the lifting method statement and in the design of erection engineering. Bolt report based on the assembly mark helped the rigging team to have control over bolt usage. 3D global coordinates taken from the Tekla model were utilized for erecting the diagrid assemblies at their exact position. The 3D model was also given to the cladding team to work out the design of the cladding system. The model was used to coordinate with the architectural profile model to nullify the interface issues. Thus the model generated in Tekla Structures had played a vital role in the successful completion of the works in a safe and faster way.

Back to top

Carbon boiler plant 11, GermanyVote

Ingenieurbüro Dipl. Ing. Klaus Mayer

Designed completely by BIM
Engineering office Ingenieurbüro Dipl.-Ing. Klaus Mayer modeled the new carbon boiler plant for general contractor, utilities of city of Kaiserslautern. The whole building, including parking area, was modeled in Tekla Structures. In the summer 2009, as the Tekla Germany model competition was ongoing, the plant was still under construction. Materials used in this model are steel and concrete. BIM was utilized in the whole planning and construction process. The boiler plant was designed completely in Tekla Structures, there were no architectural data imported as reference. All the structures were modeled in Tekla Structures. Tekla Structures Web Viewer was used in the project as an over-all communication tool between all project parties.

Back to top

Castle House Wind Turbines, UKVote

Bourne Engineering Limited

Sharing the model was critical
The Castle House is a 43-storey residential tower and will stand 147 meters high providing 310 new apartments. This entry is for the wind turbine enclosure that sits on top of the tower. The housing for the turbines is a complex curved structure supporting the cladding system and the turbines themselves which are 9 meters in diameter. Because of the complex nature of the structure, it was critical that the as-built model could be shared with the cladding specialists to ensure there were no problems on site and that Bourne Engineering could take information from the turbine manufacturers to ensure the unique basketry was in the correct positions to ensure a first time fit.

Back to top

重庆温室植物园,法国                                   (VoteChongqing Arboretum Greenhouse, France)

Marchegay

非对称弯曲的隧道
整个植物园是由非对称弯曲隧道组成,每个隧道半径各不相同。中央大厅位于两侧隧道的温室交叉处,由三个不同弧形的从地基中引出的半圆组成。使用铝和玻璃制成的一个全封闭的弧形遮阳系统,其主体结构由镀锌圆管组成,结构用钢量为736吨+58吨的室内墙(不包括接合模型)。

部分结构从法国制造运往中国
这个项目涉及到4个部分的钢结构详图,从一开始就使用Tekla Structures多用户协同工作的模式。这个项目由三部分组成:主大厅的两个拱门和在每个主大厅两侧的其他拱门。铝合金和机械的部分以及遮阳系统由五个钢结构详图深化人员完成。钢结构部分由使用Tekla Structures的一家中国公司制作,他们收到3个部分所对应得Tekla模型进行制作。所有铝合金部分都由法国加工制作,项目的管理人员只需要拥有Tekla Structures浏览器的授权就可以很好地完成监督校核的工作。

Back to top

CIDCO Exhibition Center, IndiaVote

inSTEEL ENGINEERS PVT. LTD.

Preferred venue for green conferences
The Exhibition Center is providing quality exhibition and business facilities in the Mumbai metropolitan region, and would also be the preferred venue for green/eco conferences and a permanent green awareness gallery. All profiles are hollow circular, rectangular or square sections, procured from UK, Japan & Korea, due to high yield strength of material. The required lengths had to be matched as per rolled lengths available, and the material list was preparedaccordingly. After the procurement of the material, the received lengths were compared and matched with the actual lengths as per the fabrication drawings, and the two matched almost perfectly. This resulted in bare minimum wastage and hence cost savings. This fact was highly appreciated by the client. All connections are non-conventional type and were required to be developed and also placed in the model individually.

Managing complex geometry and interoperability
"The main reason for adopting Tekla Structures 3D BIM technology is complex geometry of the said structures having semi parabolic shape, and interoperability was the another major requirement", says Raju Jagtap, Director of inSTEEL ENGINEERS Pvt. Ltd. "We have used the model to interact with structural consultant, civil contractors as well as roofing contractors. The design of roof and structural members likes tubular trusses of MS tubes/boxes is innovative. Tekla Structures is easy to use and available macros help create such a complex geometry in the shortest span of time which leads to save hundreds of man-hours. Another major challenge was modeling facades and roofing elements over these structures. This major requirement has been successfully achieved by using Tekla's best interoperability functionality to get real time full visualisation of the whole structure."

Back to top

CO naar Stoom, BeneluxVote

NEM

Toxic gas combusted into carbon dioxide
In the beginning of 2008, NEM kicked off the engineering of a CO-boiler for an oil refinery. A fluid catalytic cracker installation for oil is producing high amounts of carbon monoxide. This highly toxic gas both for humanity and environment will be combusted through our installation into carbon dioxide. The CO-boiler is in fact a big heat exchanger (up to 1100°C) to generate steam. Hot gasses are being transferred through the boiler through a circuit of steel water pipes. In this way the heat efficiently converts water into steam. The steam is used to drive a steam generator or is used for other process purposes.

Subcontracting based on the model
A case study has been carried out on the consequences of heavy earthquake loads on the boiler steel support structure. The final calculation model has been used to put up a 3D-layout model within a short period of time. The latest version 15.0 of Tekla Structures proved itself in this; especially the single-click mouse option increased the work speed. The gastight boiler outside casing ensures safe and efficient passing through of the toxic flue gasses. The big round gap is the connection to the burner unit in front of the boiler. Hot flue gasses will pass through the inlet ducting to the boiler internals, the circuit of steam/water pipes. On the rear end the cooled down gasses are disposed to a stack. Different levels of platforms and ladders provide necessary accessibility to the boiler. The steel structure next to the boiler houses the systems to service the boiler internals. Based on this model different parts have been subcontracted for detail engineering and production. This model has also provided visualization of the boiler design development towards the client and has been used for important clash checking within the total plant layout. Great advantage is the possibility to import various types of 3D files without directly overloading a computer.

Back to top

Darling Downs Power Station, AustraliaVote

Steel Fabrications Australia

Comprehensive delivery of composite concrete and steel
This project consisted of the supply, fabrication, and protective coating of 2,300 tons of structural steel and composite flooring systems. There are two main buildings in the contracted works. The first called the CTG Building houses three gas turbines comprising of 900 tons of structural steel. The second is the STG or the steam turbine building consisting of main building structural steel and a series of levels of composite concrete and steel floors throughout. Walkways and access platforms throughout the project have also been supplied by Steel Fabrications Australia. The company also provided all the pipe racks required by the power station for both the transporting of liquefied natural gas and the delivery of steam to the condensation and reclaiming structures.

Phasing of assemblies ensured erectable deliveries
The BIM benefits for this project include importing data from Tekla to FabTrol software (at least a 85-90% time saving for each release of drawings) to obtain doc control and BOM. For production, there was a 50% saving with retrieving of data from FabTrol saving 80% of time when request. Purchase order and tracking saving of 60% with less waste of material via FabTrol optimisation. Tekla Structures was cusyomized to suit the high quality of drawings required by the workshop, which enabled the fabrication to follow through the shop with ease. Phasing the assemblies through Tekla allowed steel to be ordered and fabricated to ensure delivered steel is in an erectable sequence. Important to this project as Steel Fabrication Australia was not the rigging contractor. Clarity of drawings produced from Tekla on complex assemblies ensured accuracy of fabrication.

Back to top

DBCT 7X OL3 Onshore Including Surge Bin SB3, AustraliaVote

Suresteel Detailing

Structural steel, platework surge bin and mechanical items
Construction of the onshore outloading system for the DBCT 7X project at Dalrymple Bay Coal Terminal South of Mackay (Qld). The project involved the construction of three conveyors, L11, L11A & L13, Drive Tower L11/L11A and the surge bin SB3 and sample plant SP3 building plus modifications and upgrades through the existing transfer towers. The model comprises of structural steel, platework surge bin, and mechanical items including head frames, pulleys frames, skirts, guards and some chute components.

BIM collaboration ensured positive project outcome
The DBCT Surge Bin SB3 & Sample Plant SP2 complex was undertaken in 2007/2008 to be modeled using Tekla Structures 12.1 and utilized BIM processes in conjunction with other steel detailers using a different software product (AutoCAD-based 3D system) and equipment suppliers for the project. The information transfer between the other steel detailers worked both ways, with Suresteel Detailing providing them with 3D DWG versions of the model for them to undertake the piping and some other aspects of their scope. Their information was then referenced into the Surge Bin model to ensure there were no clashes and the interfaces all met up correctly. The 3D models were also sent to the drive suppliers to enable them to design the hydraulic piping routes and pipe supports for their installation works on the project. The use of BIM processes and collaboration between parties ensured an effective and positive project outcome.

Back to top

Estadio Chivas, MexicoVote

Heimsa

Roof of curved and straight round tubes
This is a roof structure of a new soccer stadium in the city of Guadalajara, for the world famous Chivas soccer team, which also owns a franchise in the United States called Chivas USA. The main members are all curved round tubes, the secondary ones straight round tubes and purlins. The design and the erection sequence were planned around dividing the overall structure in four quadrants, each consisting of three full and two half subdivisions called modules. The two half modules were shared, half each, by two adjacent quadrants. The overall structure is supported by 16 concrete columns. The curved structure itself is 190' wide and 36' deep, the overall structure is about 600' x 900'.

Major savings in shop engineering
Tekla Structures was used to detail the project after a Staad design model was imported, and was also used to create an architectural IFC model that was later incorporated in a Revit architectural model. The unique connections required several custom components to be created to adapt to the many occurrences in the overall project. By using the unique 3D representation in Tekla Structures and the accurate dimensioning tools in drawings one person was able to accomplish the shop engineering in the same period of time it would have taken a team of several people using other detailing methods.

Back to top

2010世博会中国馆     (Expo 2010 Pavilion, ChinaVote)

上海同清科技发展有限公司

两个半足球场大小的国家场馆
T中国馆总建筑面积达16.01万平方米,由中国国家馆、地区馆等组成。国家馆层叠出挑,呈拱斗形,体现了“东方之冠、鼎盛中华,天下粮仓、富庶百姓”的文化理念。其主体结构由4个钢筋混凝土核心筒立柱和钢结构组成,其中钢结构与地面间的悬挑高度达35米,顶盖面积达1.96万平方米,相当于两个半足球场。国家馆高63米,架空层高33米,架空平台高9米,上部最大边长为138米乘以138米,下部四个立柱外边距离70.2 米,建筑面积约为2.7万平方米。

工期紧迫复杂的钢结构
世博会中国馆由上海同清科技发展有限公司使用Tekla Structures进行建模。纵观整个项目,钢结构部分是最复杂的,该项目工期紧、设计变更多。Tekla Structures强大的节点处理能力和多用户协同工作模式给工程进度节省了时间,模型和图纸的永久关联保证了构件准确的制造。Tekla在技术和质量上获得承包商和项目业主的一致好评。

Back to top

2010世博会演艺中心,中国Vote                                     (Expo 2010 Performance Center, China)

冠达尔钢结构有限公司

在草地上徘徊的飞碟
2010年上海世界博览会演艺中心,位于“世博园”核心区,其用地面积67242.6平方米,总建筑面积125945平方米,高42米,总用钢量约35000余吨,是世博会最重要的永久性场馆之一。演艺中心以“飞碟”状的穿梭腾飞的形态作为建筑的主体,呈漂浮状地坐落于草坡基座上。在不同角度与不同时间会呈现出不同形态,白天如“时空飞梭”、似“艺海贝壳”,夜晚则梦幻迷离,恍如“浮游都市”。 世博演艺中心内含以大型中央舞台为主体、拥有18000座观众席的大型多功能室内演艺场馆及相关配套设施,是一个符合现代理念的文化娱乐集聚区。

通过BIM详细空间定位、加工制作和现场安装
世博演艺中心采用Tekla Structures搭建模型进行详图设计。由于该工程飞碟造型较为特殊,其中存在大量的空间结构杆件的定位及空间节点处理;而且该工程工期紧,工程量大,如采用传统的如AutoCad等软件,其工程质量和工期很难保证。通过利用Tekla Structures强大的空间三维操作功能,可以提供详尽的空间定位,为工厂加工、现场安装提供了方便;而其图纸功能及准确的零件图转化功能也为加工提供了很大的便利。应用该软件强大的报表功能,可以在工程进行的同时,为材料采购提供相对准确的料单,为工程进度提供了保障,降低了生产成本。

Back to top

Fountain oasis, Middle EastVote

Eversendai Consulting Engineers Private Ltd

The most complicated structure of the Dubai Mall
This was the most complicated structure in the Dubai Mall project in terms of modeling, editing and member application. From a technical point of view, this was a challenging job in terms of model application for connections and geometrical application in the model. The approximate tonnage is 484 million. The fascinating part of the structure is the trusses joining at the center and at verendel truss segment joint for application.

Back to top

Iron Horse Bridge, USAVote

Axis Steel

Handreils included in the model
The Iron Horse Bridge is 400 tons spanning half a mile long. It includes tons of plate work consisting of a series of 14’-0 tubs or deck pans that weld and field bolt to a series of bulkhead plates. The arches are 196’-0 long from the concrete buttress to the center field bolted splice (total arch length of 392’-0) and there are 3 round HSS pipes that are connected with a series of CP welded plate boxes. Curved, radiused arches connect to a radial box beam that supports the ends into concrete piers. A cable rod system connects the arches to the Tub in a suspension bridge type action. The bridge has 3 radii in the plan view with continual change in elevation. Axis Steel modeled in handrails, which are a series of custom plate posts that flare out and back as you go across the bridge with a cable rail system.

Complete BIM coordination with all associated trades
The Iron Horse project spans about 2 miles in length and over 8 lanes of traffic in central California, north of San Francisco. Axis Steel has had multiple model reviews and 3D CAD exports for complete BIM coordination with all associated trades on the project, including concrete and rebar. They also coordinated the special fencing that spans between the hangar rod cables within the arches that connect down to the top of the bridge chord members and are actually in a 'warped' plane. This coordination has taken place with multiple WebEx meetings with the fence company, the EOR, Architect, GC, owner's representative, and steel fabricator as well as the miscellaneous metals fabricator and specialty contractors. Axis has been able to model all trades within the Tekla model and they have used the model for accuracy, dimensional coordination, and job site review.

Back to top

Logistics and office building, GermanyVote

Steelconcept GmbH

Multimaterial turnkey project
This model is a 2000m2 office space with 4500m2 production area. The planning of the new logistics and office building of Heckert-B.T.X. Solar Company was commenced in April 2008 and the building was completed in June 2009. Several materials were used in this turnkey building: the office building consists of steel, concrete, glas, aluminium and plastic materials and the logistics hall of steel and concrete. Shed-roof structures use solar energy. Tekla Structures Web Viewer was utilized for communicating and presenting the model in different phases of the project. The interoperability of Tekla Structures enabled error-free data transfer between different subsection operators and cooperation partners, e.g. for reinforcement, HVAC, and electric planning. The Tekla 3D model also offered good representation of external planned parts of the building (the glass facade).

Back to top

罗安达体育场,安哥拉                                        (VoteLuanda Stadium, Republic of Angola)

上海立飞建筑科技有限公司

国家地标性建筑
罗安达体育场位于非洲南部的安哥拉,它是即将于2010年举行的非洲国家杯的主体育场,落成后将成为安哥拉国内最大的体育场和地标性建筑。这个建筑工程包括了运动场和相关附属设施,例如超级市场。罗安达体育场采用大跨度的建筑设计,主体结构是四周延伸的三位体系钢结构,整个造型就像非洲草原上羚羊的羊角。建成后,体育场将可以容纳5万人同时观看比赛,占地面积约6.2万平方米,整个工程使用超过10万吨的混凝土。

工程运输
罗安达体育场钢结构部分使用约8,800吨的钢材,上海建工集团作为总承包中标本工程中的所有子项目,工程中使用的所有材料和机械设备都需要通过海运从中国运往非洲。为了节省成本,制订出合理高效的工厂制造、运输计划来配合货轮出海时间就变得非常重要。利用Tekla Structures,项目管理者可以方便快速的为所有钢结构构件制定出加工计划、运输计划和码头堆放计划,BIM模型中的每个构件都可以分派不同类型的时间,并采用时间推移表的形式显示,甚至使用4D工具将整个动态过程再现。

Back to top

MODEC PB GAS FPSO, 中国Vote                              (MODEC PB GAS FPSO, China)

海洋石油工程股份有限公司

浮式生产,储存和卸载
该FPSO(浮式生产,储存和卸载)船将能够处理3.5亿每立方英尺天然气,每天35000桶石油,以及将有大约70万桶的储存容量。该船将部署在Urugua领域,也将收集Tambau油田的生产。这两个领域都是在桑托斯盆地,并正在共同发展。

通过BIM深化设计、加工制作和现场安装
的是作为一个综合的过程,大大提高了项目的了解和可预见的结果。Tekla Structures使所有项目团队成员保持协调,提高精度,减少浪费,并在确保项目的成功进程中作出明智的决定。所有的钢结构都是在Tekla Structures下建模,海洋石油工程有限公司使用这个模型进行深化设计、加工制作和现场安装。

Back to top

Onesteel Warehouse & Office Building, AustraliaVote

Pacific Drafting

No delays and nearly nil modifications
Tekla Structures was utilized for the structural steel package of the project. Using Tekla made the project efficient in everyway, providing all necessary information, including correspondence with engineers and architects, designing, checking, project management, ordering materials, fabrication, surface treatments, transport and erection. Tekla also enabled to provide information to the tilt panel detailer for ferrule and cast in plate locations. All subcontractors involved commented on the user friendly viewing, the software providing a clear understanding of the project. This project had minimal problems with no delays and almost nil site modifications to the structural steel.

Back to top

Ore storage, SwedenVote

WSP

Multi-user project of several buildings connected by conveyors
WSP Skellefteå has designed a ore storage with machine room on the top as a part of the Aitik36 mine project in Boliden Sweden. The mainframe is made of welded H-profiles with profile height of 1350mm. The assembly phase was considered already during the modeling because the area for the building is covered by big holes for collecting ore while simultaneously builiding the concrete structure for transporting the ore from the storage house. The building spans over an area of 125x70m2 and is 65m high. The model contains several 'helpobjects', like important coordinates, ore and connections to other buildings, and machinery models. This stogare is part of a bigger project that spans over several square kilometers of buildings connected by conveyors. This is a multi-user project with 3 users.

Back to top

Parking Odysseum, FranceVote

ECBA

Resting on steel tubes filled with concrete
The parking lot for 1700 cars inside a commercial center in the city of Montpellier includes a 15m wide track, the total length of which is 1600m with slopes varying from 0.2 to 4.0%. The total weight of the structure is 1900 tons. The structure is resting on pinned columns made of steel tubes filled with concrete. The stability is ensured by a collaborative slab connected by about 100,000 Nelsonvstuds and the stops against the concrete stair case.

Efficient exchange of model information
This project involved three Tekla customers: C&E ingenierie was in charge of the pre-modeling phase and Analysis&Design; the Steel Detailing offices ECBA and CABROL CM were in charge of the fabrication and erection and partly the steel detailing of the ironworks. All of these disciplines exchanged their Tekla models to benefit from existing design and detailing. In addition, the team used Tekla Structures Viewer during the erection phase.

Back to top

Sheikh Zayed Mosque, Middle EastVote

Galadari Engineering

Dome part of the mosque
The model was done by Galadari Engineering Works Ltd. Co. (L.L.C.). This dome is a part of Sheikh Zayed Bin Sultan Al Nahyan Mosque in Abu Dhabi, the UAE, and created in Tekla Structures version 10.2.

Efficient procurement and coordination
Followng the BIM concept helped GEW in effecient procurement of material, fabrication and erection as per sequence requirement and timely completion. BIM also helped to coordinate with architectural and other elements of the dome, such as false ceiling, walkway, and ladder, in an efficient way.

Back to top

 
深圳世界大学生运动会体育馆,中国               (Shenzhen Universiade Sports Center Main Stadium, C) Vote

上海浩荣建筑科技有限公司


大型多功能体育馆
        深圳世界大学生运动会体育馆是2011年世界大学生运动会的主体育馆,这是一个多功能体育馆,可以举办羽毛球、体操、篮球、排球、室内短道速度滑冰等多个项目,以满足各种国际比赛和个别综合锦标赛的功能要求。体育馆的每个单片建筑都采用空间弯曲钢架结构作为基本要素,水晶般的墙壁和富有表情的屋顶建筑,都让这个体育场饱含活力。体育馆的屋顶高度为30.5m,建筑面积约7400平方米,可以同时容纳1.8万人,是一个相当大的室内体育场馆。

方便对复杂造型建模
        使用Tekla Structures软件,可以方便地对复杂几何造型建筑进行建模,就像这个体育馆。利用软件提供的捕捉和定位功能,能够容易的将杆件放置到准确的位置,然后利用软件内丰富的系统节点库和自定义用户节点功能,Tekla Structures能让工作变得高效、准确。“在我使用Tekla Structures建模的时候,它强大的节点功能帮助我方便地创建各类节点,整个项目的项目设计在2个月内就完成。”上海浩荣建筑科技有限公司张伟经理向我们介绍说。

Back to top

Student entry, GermanyVote

Husein Kurtovic, Aachen University of Applied Sciences, Civil Engineering

Column free jumbo jet hangar
The winner of the first Tekla Germany model competition is an entry of a student of civil engineering at the Aachen University of Applied Sciences. The existing jumbo jet hangar was modeled in Tekla Structures as part of master thesis. Because of the size of the Boeing 747 airplanes, the main requirement for the building was to be built totally column free. Special feature of the building is a double-arch which goes 55m above the building floor and forms the main plane structure. Two trussed beams adjust the horizontal thrust. These together with the orthogonal secondary beams build the support grid of the entire hangar. Three stiffening girder telescoping parallel with the trussed beams strengthen the support grid. Vertical supporting loads of the double-arch have been adjusted by four brackets. Furthermore, vertical load is being given off from the secondary beams to the back wall and from the trussed beams and the stiffening girder to the flank wall. In the hangar model BIM was utilized first of all in the input of the data from an already existing building.

Back to top

The Fietsappel, BeneluxVote

Iv-Consult

Heavyweight engineering enabled lightweight design

The Fietsappel is a very special kind of bicycle garage in Alphen aan den Rijn in The Netherlands. Approximately 1000 bicycles can be parked in this garage. Its apparently simple basic form (an apple) is somewhat misleading as its three dimensional design is, in fact, highly complex. The ramp on which the bicycles are parked is spiralled like an apple peel around a cone-shaped core of steel columns. The outer shell is made from transparent lace fence. Due to the complex three-dimensional structure of this unique design, not one element is the same. The best material to build this structure with is therefore steel. This lightweight design nevertheless requires a heavyweight engineering approach. Iv-Consult was responsible for the calculations, design, detailed calculations and shop drawings.

Back to top

The Pinnacle Tower, UKVote

Ove Arup and Partners International Limited

Successful transfer of model information
The Pinnacle Tower will for a while be the tallest structure in London with its outstanding modern architecture standing at an impressive 288 meters high with 62 floors above ground level and 3 basement levels. Its ventilated façade system consists of overlapping flat panels designed to resemble snakeskin. The model itself was started in Arup's own Analysis & Design software Oasys GSA and was originally passed into 3D+ software where the model was continued. Later the model was moved into Tekla Structures via the Tekla 3dn import and continued there for drawings and also exported to the steelwork contractor via SDNF. The model has been received back from the steelwork contractor for review and approval along with the drawings.

Back to top

Transport Barge, Middle EastVote

Lamprell Energy Limited

Platform maintenanc and well intervention
The transport boat concept has been in use for quite a number of years. These barges are a proven concept and there are a number of them operating around the world showing that they are a cost effective method for platform maintenance and well intervention. The barge is shown as transporting a module to be installed on an FPSO. The barge is also capable of carrying complete drilling equipment with the drill strings for installation on a jacket and performs the drilling with sufficient power and utilities from the barge.

Extensive use of custom components
Lamprell is likely to be the first to use Tekla Structures for fabrication detailing for a barge. They used a number of custom components for creating panels, making cut-outs on bulkheads, preparing pipe sleeves, haunch plates, nodes, etc. Tekla custom components were used to create weld preparations with great ease and generate fabrication sequences. The Tekla model helped in identifying clashes within steel, tertiary, weld accesses, etc. Profiled Bilge Keel plates were successfully modeled and developed for forming in this project.

Back to top

Yas Island Yacht club, Middle EastVote

National Engineering Services

Prestigious administration building
Yas Island building is Abu Dhabi’s prestigious administration and commercial building project. Tekla BIM technology helped to model the building with ease to achieve ayster shape hard shell roofing wrapping over the building and enclosing the transparent fluid glass facades within. The main challenge was to achieve this building’s complex architectural shape which is carved out to reveal the inner facades, which is reminiscent of Abu Dhabi’s maritime culture of wooden boards with triangular sails. Tekla Structures allowed to model such a great shape with the overhanging roof acting as a canopy, the shell type roofing form the encasing.

Back to top